Electrical & Low Voltage

Division 26 / 27 / 28 · 4 bidders · Budget $10,250,000 · Updated 8/17/26
Leveled
13
Requests
5
Awaiting reply
4
Overdue
8
Answered

Requests

RFI cutoff 7/31/26 · bids due 8/12/26
  1. Answer · 8/17/26

    Encasement at $41.00 per linear foot, material and labour, based on the 480 LF.

  2. Answer · 8/15/26

    Called to confirm. Carried at $194,000 for 22 months, all trades, and it assumes the Phase 2 pads run concurrently. If the pads are deferred they will credit the difference at the monthly rate. Asked them to put it in writing.

  3. Answer · 8/15/26

    Our figure covers our own crews and the panel at the job trailer. Distribution to other trades is not carried and would be an add of $84,000 for the full duration.

  4. Answer · 8/14/26

    We carry the conduit and the sand bedding. Trench, backfill and compaction are by the site contractor. We will coordinate the open trench schedule.

  5. Answer · 8/14/26

    Addendum 8 fixture is carried. No change to the base bid.

  6. Answer · 7/31/26

    The utility will permit two daytime shutdowns of eight hours each, coordinated through the owner. Night work is not required.

  7. Answer · 7/30/26

    Encasement is required under paved areas only, approximately 480 LF. Elsewhere direct burial with sand bedding is acceptable per detail 4/E1.4.

  8. Answer · 7/29/26

    See attached SK-04. Pole base is a 24" diameter cast-in-place pier, 6'-0" deep, furnished and placed by the concrete trade. Anchor bolt template and conduit stub-up by the electrical trade.

33 open questions on this package. 7 have been sent, 3 answered, 26 not yet sent. A request carries the answer back to the cell that produced it, so the record of what was asked sits on the sheet rather than in an estimator’s inbox.