Larkspur Commons

Vantage Retail Partners · 42 bid packages · 28 in bidding · Updated 8/17/26
DivisionPackageBiddersStatusBudgetLow adjustedVarianceCoverageUpdated
01Surveying & Layout2Awarded$256,000$241,000($15,000)—6/18/26
01Temporary Facilities & Controls3Awarded$851,000$878,000$27,000—6/20/26
02Demolition & Abatement3Awarded$1,360,000$1,290,000($70,000)—6/26/26
03Cast-in-Place Concrete4Bids received$9,560,000———8/14/26
03Precast Concrete2Awaiting bids$2,480,000———8/6/26
04Masonry3Bids received$2,080,000———8/12/26
05Structural Steel & Misc Metals3Bids received$7,450,000———8/15/26
05 / 09Framing, Drywall & Plaster4Bids received$13,030,000———8/15/26
06Rough Carpentry2Awaiting bids$1,650,000———8/4/26
06Architectural Millwork3Awaiting bids$2,310,000———8/5/26
07Waterproofing & Sealants2Awaiting bids$952,000———7/30/26
07Building Insulation3Bids received$707,000———8/7/26
07Metal Wall Panels2Awaiting bids$2,030,000———8/1/26
07Roofing—Not yet issued$3,790,000———7/24/26
07Firestopping1Awaiting bids$352,000———8/3/26
07Expansion Joint Assemblies—Not yet issued$215,000———7/19/26
08Doors, Frames & Hardware2Awaiting bids$1,620,000———8/7/26
08Storefront & Glazing3Bids received$5,190,000———8/13/26
08Overhead & Coiling Doors2Awaiting bids$775,000———8/4/26
08Louvers & Vents—Not yet issued$194,000———7/17/26
09Acoustical Ceilings3Bids received$1,330,000———8/11/26
09Tile3Bids received$1,034,000———8/9/26
09Flooring4Bids received$2,750,000———8/12/26
09Painting & Coatings3Bids received$1,280,000———8/10/26
10Toilet Partitions & Accessories2Awaiting bids$443,000———8/2/26
10Signage & Wayfinding—Not yet issued$414,000———7/21/26
11Loading Dock Equipment2Awaiting bids$622,000———7/28/26
11Food Service Equipment—Not yet issued$1,500,000———7/23/26
12Casework & Countertops2Awaiting bids$835,000———8/3/26
12Window Treatments—Not yet issued$293,000———7/20/26
14Elevators & Escalators2Bids received$3,110,000———8/9/26
21Fire Sprinkler3Awarded$2,060,000$2,080,000$20,000—7/31/26
22 / 33Plumbing & Underground Utilities3Bids received$5,640,000———8/14/26
23HVAC & Controls3Bids received$7,340,000——78%8/16/26
26 / 27 / 28Electrical & Low Voltage4Leveled$10,250,000$9,128,400($1,121,600)70%8/17/26
31Trenching & Excavation2Awaiting bids$3,130,000———8/11/26
31Earthwork & Grading4Awarded$4,670,000$4,740,000$70,000—7/2/26
31Shoring & Sheet Piling2Awarded$1,440,000$1,500,000$60,000—7/6/26
32Landscaping & Irrigation3Awarded$2,700,000$2,750,000$50,000—7/18/26
32Asphalt Paving & Striping3Awaiting bids$3,380,000———8/8/26
32Fencing & Gates—Not yet issued$638,000———7/22/26
33Site Utilities3Bids received$3,460,000———8/13/26

14 of 42 packages carry fewer than 3 bids. Packages not yet issued are not counted.

Coverage is scope items responded to across all bidders, over items times bidders, graded against each package’s scope template. Packages without a template show no coverage.