Electrical & Low Voltage

Division 26 / 27 / 28 · 4 bidders · Budget $10,250,000 · Updated 8/17/26
Leveled
Low bid
$7,680,000 Tallman
Gap, first to second
$970,000
Spread
$2,870,000 37.37% of low
Excluded or not addressed, low bidder
$1,394,500
Description
Tallman
Letter, 1 pp
44 of 118 addressed
Ridgeway
Letter, 4 pp
71 of 118 addressed
Corbin
QAS form, 4 pp
118 of 118 addressed
Halden
Letter, 6 pp
96 of 118 addressed
Phase 1
Site lighting fixture package
Site electrical
Site dry utilities & telecom (new service)
Site dry utilities & telecom (relocation)
Anchor Building lighting fixture package
Anchor Building electrical
Anchor Building fire alarm system
Anchor Building fire alarm box & conduit
Central Plaza & Pavilion lighting fixture pkg
Central Plaza & Pavilion electrical
Conduit for fire alarm cables
Phase 1 subtotal$4,270,000#2$4,930,000#3$4,190,000#1$6,080,000#4
Phase 2
Retail pad sitework electrical
Pad A lighting fixture package
Pad A electrical
Pad B lighting fixture package
Pad B electrical
Pad C lighting fixture package
Pad C electrical
Shops 1-3 lighting fixture package
Shops 1-3 electrical
Shops 4-5 lighting fixture package
Shops 4-5 electrical
Phase 2 subtotal$3,410,000#1$3,720,000#2$5,070,000#4$4,470,000#3
Alternates
Alternate 1 & 2 - pole & pull box relocation, Sheets E1.2 through E1.4
Alternate 3 - entry approach area electrical
Alternate 4 - EV charging rough-in, 6 stalls
Unit Costs
Concrete encasement, 2" and larger conduit/LF
Journeyman electrician, straight time/hr
Fixture add or delete, interior LED troffer/ea
Assumptions, Exclusions & Clarifications
Excavation, backfill & trenching for own work
Main distribution switchboard, furnish
Seismic & structural supports
Conduit & wire for HVAC equipment
Concrete encasement, 2" and larger conduit
Arc flash, short circuit & coordination study
Barricades, flagging & traffic control
Temporary power & lighting for own work
Temporary power & lighting, all trades, full durationout of basis
Joint sealants & firestopping at own penetrations
Cast-in-place cable vault & pad
Lighting control commissioning & Title 24 acceptance
Owner-furnished fixture install allowanceout of basis
Commercial Terms
P&P bond rate
Escalation carried
Proposal validity
Addenda acknowledged
Base Bid$7,680,000$8,650,000$9,260,000$10,550,000
Total Adjusted Bid w/o P&P Bond$7,680,000$8,650,000$9,260,000$10,550,000
Budget Variance($2,570,000)($1,600,000)($990,000)$300,000
Budget Variance %-25.07%-15.61%-9.66%2.93%
Low Bid Variance$0$970,000$1,580,000$2,870,000
Low Bid Variance %0.00%12.63%20.57%37.37%
Rank1234

A bidder’s base bid is the sum of their numeric cells. yes means carried in the lump sum and not broken out, and contributes zero to the column. Alternates and unit costs display but do not enter the base totals.

Every cell and every adjustment opens to the clause it was read from. Click any cell.