Electrical & Low Voltage
Division 26 / 27 / 28 · 4 bidders · Budget $10,250,000 · Updated 8/17/26
Leveled
Bidder
Lowest adjusted bid
$9,128,400
Tallman · as submitted $7,680,000
Gap, first to second
$65,100
as submitted $970,000
Spread across four bids
$945,600
10.36% of low · was 37.37%
Unpriced, lowest bidder
$1,394,500
excluded or not addressed by Tallman
Bid position against budget
Each bidder as submitted and after leveling. Rank order does not change; the gap does.
- As submitted
- Leveled
Leveling bridge, Tallman Electric Co.
9 adjustments carry the base bid to the adjusted total.
- Add-back
- Out-of-basis deduct
- Overridden
Scope coverage
118 template items, Div 26 / 27 / 28. Counts, not dollars.
- Carried
- Excluded in writing
- No response
Rank by phase
Corbin is the cheapest bidder in Phase 1 and the most expensive in Phase 2, an $880,000 swing inside one package.
Where the leveling dollars come from
Adjustment value by basis. Coverage counts items; this counts money.
- Excluded
- Not addressed
- Bidder stated add
- Out-of-basis deduct
Every figure on this page is derived from the leveling sheet, which is the table view for all of it. No chart introduces a number that is not on the sheet.