Electrical & Low Voltage
33 questions, each carried back to the cell, scope item or commercial term that produced it. 7 sent, 3 answered, 26 not yet sent.
Tallman Electric Co.
14 questionsestimating@tallman-electric.example- 1.
Fire alarm devices, wiring, panel and programming are excluded while fire alarm conduit and boxes are included. Confirm the division of the fire alarm scope and identify who is expected to furnish devices and programming.
AwaitingPR-009 · sent 8/15/26Anchor Building fire alarm systemFire alarm devices, wiring, panel and programming are excluded. Conduit, boxes and pull wire for the fire alarm system are included.Leveling sheet · Tallman Electric Co. proposal, p. 1 - 2.
Excavation, backfill and trenching for own work is excluded. State who is expected to trench, bed, backfill and compact for the site conduit shown on E1.1 through E1.6.
AnsweredCLR-031 · sent 8/13/26Excavation, backfill & trenching for own workExcluded from this proposal: excavation, backfill, trenching, shoring and compaction, including for our own conduit.Leveling sheet · Tallman Electric Co. proposal, p. 1 - 3.
Switchgear and main distribution equipment are excluded as furnished by others. Confirm that installation, termination and startup of that equipment are carried.
OverdueCLR-032 · sent 8/13/26Main distribution switchboard, furnishExcluded from this proposal: switchgear and main distribution equipment, furnished by others. Installation and termination are included.Leveling sheet · Tallman Electric Co. proposal, p. 1 - 4.
Seismic calculations, structural supports and anchorage design are excluded. Confirm whether deferred-approval seismic submittals are expected from the structural engineer of record.
Not yet sentSeismic & structural supportsExcluded from this proposal: seismic calculations, structural supports, and anchorage design.Leveling sheet · Tallman Electric Co. proposal, p. 1 - 5.
Conduit, wire and connections to HVAC equipment are excluded. Confirm the scope split with the mechanical contractor at rooftop units, VFDs and controls panels.
Not yet sentConduit & wire for HVAC equipmentExcluded from this proposal: conduit, wire and connections to HVAC equipment, by the mechanical contractor.Leveling sheet · Tallman Electric Co. proposal, p. 1 - 6.
Concrete encasement of 2" and larger conduit is not addressed. State whether encasement is carried, and at what quantity, for the duct bank shown on E1.4.
Not yet sentConcrete encasement, 2" and larger conduitBase bid is a lump sum for the electrical work shown on drawings E0.1 through E9.4 dated 06/24, addenda 1 through 8, exclusions as listed below.Leveling sheet · Tallman Electric Co. proposal, p. 1 - 7.
Alternates 1 through 4 are not addressed. Provide pricing for each alternate or state no bid on each.
Not yet sentAlternate 1 & 2 - pole & pull box relocation, Sheets E1.2 through E1.4Base bid is a lump sum for the electrical work shown on drawings E0.1 through E9.4 dated 06/24, addenda 1 through 8, exclusions as listed below.Leveling sheet · Tallman Electric Co. proposal, p. 1 - 8.
Unit costs are not addressed. Provide unit costs for concrete encasement per linear foot, journeyman electrician straight time per hour, and interior fixture add or delete per each.
Not yet sentConcrete encasement, 2" and larger conduitBase bid is a lump sum for the electrical work shown on drawings E0.1 through E9.4 dated 06/24, addenda 1 through 8, exclusions as listed below.Leveling sheet · Tallman Electric Co. proposal, p. 1 - 9.
The lighting fixture packages are carried in the lump sum but not broken out. Provide the fixture package value for each of the six areas on the bid form.
Not yet sentSite lighting fixture packageOur lump sum includes all labor, material and equipment for the electrical work shown, including site lighting fixture package.Leveling sheet · Tallman Electric Co. proposal, p. 1 - 10.
Division 27 communications work is not addressed. State whether pathways, conduit, back boxes and telecom room backboards are carried.
Not yet sent27 05 00 Communications pathways, conduit and back boxesNo response in the proposal.Scope coverage - 11.
Division 28 access control and video surveillance rough-in is not addressed. State whether conduit, back boxes and line voltage to security equipment are carried.
Not yet sent28 13 00 Card reader rough-in and back boxesNo response in the proposal.Scope coverage - 12.
Escalation is not stated. Confirm whether material escalation is carried through the 130 week duration, and identify the commodities at risk if it is not.
Not yet sentEscalation carriedBase bid is a lump sum for the electrical work shown on drawings E0.1 through E9.4 dated 06/24, addenda 1 through 8, exclusions as listed below.Commercial terms · Tallman Electric Co. proposal, p. 1 - 13.
Proposal validity is 30 days. Confirm the price can be held to the scheduled award date, or state the escalation that applies past 30 days.
Not yet sentProposal validityThis proposal is valid for 30 days from the date above.Commercial terms · Tallman Electric Co. proposal, p. 1 - 14.
Bond rate is 1.10%, the highest of the four proposals. Confirm the rate is firm and identify the surety and single-job bonding capacity.
Not yet sentP&P bond ratePayment and performance bond is excluded. Add 1.10% of contract value if required.Commercial terms · Tallman Electric Co. proposal, p. 1
Ridgeway Electric
9 questionsestimating@ridgeway-electric.example- 1.
No addenda are acknowledged and the proposal is priced off the plan set dated 06/24. Confirm addenda 1 through 8 are included, or provide the cost impact of each.
OverdueADD-004 · sent 8/13/26Addenda acknowledgedThis proposal covers Phase 1 and Phase 2 electrical as shown on the plan set dated 06/24. No addenda were available to us at the time of pricing.Commercial terms · Ridgeway Electric proposal, p. 1 - 2.
Fire alarm control panel, devices, wiring and programming are excluded while fire alarm raceway is included. Confirm the raceway scope covers all three fire alarm rows on the bid form.
Not yet sentAnchor Building fire alarm systemExclusions: fire alarm control panel, devices, wiring and programming. Fire alarm raceway is included.Leveling sheet · Ridgeway Electric proposal, p. 2 - 3.
Seismic bracing, structural supports and anchorage engineering are excluded. Confirm whether supports are expected from the structural subcontractor.
OverdueCLR-037 · sent 8/14/26Seismic & structural supportsExclusions: seismic bracing, structural supports and anchorage engineering.Leveling sheet · Ridgeway Electric proposal, p. 4 - 4.
Concrete encasement is not addressed although a unit cost of $43.00 per linear foot is provided. Confirm the encasement quantity carried in the base bid.
Not yet sentConcrete encasement, 2" and larger conduitThis proposal covers Phase 1 and Phase 2 electrical as shown on the plan set dated 06/24. No addenda were available to us at the time of pricing.Leveling sheet · Ridgeway Electric proposal, p. 4 - 5.
Barricades, flagging and traffic control are not addressed. Confirm whether traffic control is carried for both phases at the Larkspur Parkway frontage.
Not yet sentBarricades, flagging & traffic controlThis proposal covers Phase 1 and Phase 2 electrical as shown on the plan set dated 06/24. No addenda were available to us at the time of pricing.Leveling sheet · Ridgeway Electric proposal, p. 4 - 6.
Arc flash, short circuit and coordination study and labels are excluded. Provide a priced add for the study and labels.
Not yet sentArc flash, short circuit & coordination studyExclusions: arc flash study, short circuit study, coordination study and labels.Leveling sheet · Ridgeway Electric proposal, p. 4 - 7.
Escalation is not carried and material pricing is stated as adjusted at billing against a published index. Identify the index, the base date and the cap.
Not yet sentEscalation carriedMaterial escalation is not carried. Copper, aluminum and gear pricing will be adjusted at time of billing against published index.Commercial terms · Ridgeway Electric proposal, p. 1 - 8.
Equipment pads and housekeeping curbs are excluded. Confirm these are expected from the concrete subcontractor and identify the pads required.
Not yet sent26 05 00 Equipment pads and housekeeping curbsExcluded in writing.Scope coverage - 9.
Backbone and horizontal cabling are excluded. Confirm the Division 27 split and state whether pathways and back boxes remain in the base bid.
Not yet sent27 13 00 Backbone fiber optic cableExcluded in writing.Scope coverage
Corbin Electrical Contractors
4 questionsbids@corbin-electrical.example- 1.
Temporary power and lighting is excluded as by general contractor. Confirm whether temporary power for own work is expected from Northgate, and provide a priced add if it is not.
AnsweredCLR-038 · sent 8/14/26Temporary power & lighting for own workTemporary power and lighting - excluded, by general contractor.Leveling sheet · Corbin Electrical Contractors, quotation analysis form, p. 4 - 2.
Joint sealants and firestopping at own penetrations are excluded. Confirm the trade expected to firestop electrical penetrations at rated assemblies.
Not yet sentJoint sealants & firestopping at own penetrationsJoint sealants at own penetrations - excluded, by others.Leveling sheet · Corbin Electrical Contractors, quotation analysis form, p. 4 - 3.
Alternates 1 and 2 are carried in the base bid at $97,000 and $52,000. Confirm both values so the scope can be removed for comparison against the other three proposals.
Not yet sentAlternate 1 & 2 - pole & pull box relocation, Sheets E1.2 through E1.4Alternate 1, pole relocation, $97,000, and Alternate 2, pull box and vault relocation, $52,000, are carried in our base bid.Leveling sheet · Corbin Electrical Contractors, quotation analysis form, p. 3 - 4.
Utility company fees, dewatering and shoring, cutting and patching, and off-hours premium time are excluded. No bidder carried these four items. Confirm they belong to Northgate scope.
Not yet sent26 05 00 Utility company fees, charges and connection costsExcluded in writing.Scope coverage
Halden Electric
6 questionsestimating@halden-electric.example- 1.
Entry approach and signalization area electrical is carried in the base bid rather than quoted as Alternate 3. Confirm the $249,000 value so the scope can be removed for comparison against the other three proposals.
Not yet sentAlternate 3 - entry approach area electricalEntry approach and signalization area electrical, $249,000, is included in our base bid rather than quoted as Alternate 3.Leveling sheet · Halden Electric proposal, p. 4 - 2.
Temporary power and lighting for all trades for the full duration is carried in the base bid. Confirm the $194,000 value, the duration assumed, and the demarcation from temporary power for own work.
AnsweredCLR-035 · sent 8/14/26Temporary power & lighting, all trades, full durationTemporary power and lighting for all trades for the full duration of the work, $194,000, is included in our base bid. Temporary power for our own work is included separately.Leveling sheet · Halden Electric proposal, p. 6 - 3.
An installation allowance for owner-furnished fixtures is carried at $105,000. Confirm the fixture count and types the allowance covers.
Not yet sentOwner-furnished fixture install allowanceInstallation allowance for owner-furnished fixtures, $105,000, is included in our base bid.Leveling sheet · Halden Electric proposal, p. 6 - 4.
Barricades, flagging and traffic control are excluded for Phase 2 only. Confirm the Phase 1 traffic control scope carried and the reason for the split.
Not yet sentBarricades, flagging & traffic controlNot included: barricades, flagging and traffic control during Phase 2. Phase 1 traffic control is included.Leveling sheet · Halden Electric proposal, p. 6 - 5.
Arc flash, short circuit and coordination study and warning labels are excluded. Provide a priced add for the study and labels.
Not yet sentArc flash, short circuit & coordination studyNot included: arc flash, short circuit and coordination study, or arc flash warning labels.Leveling sheet · Halden Electric proposal, p. 6 - 6.
Escalation is not included and commodity claims are reserved on copper, steel conduit and switchgear. Identify the trigger, the index and the notice period for a claim.
Not yet sentEscalation carriedEscalation is not included. We reserve the right to claim commodity increases on copper, steel conduit and switchgear.Commercial terms · Halden Electric proposal, p. 1